													September 22, 2002P.S. Du Pont Hall dedication
May 2002
													April 2002
													March 2002Restoration of the Green landscaping and pavers in is progress; Ceramic tile
installation is complete in the toilet rooms and accessories installation is
in progress; Millwork installation has begun in the Dean's Suite and the
Lobby.
February 2002Limestone steps and pavers are complete at the west entrance; Drywall
installation is complete on all floors; Ceramic tile is being installed in
the toilet rooms; Sheet vinyl installation has begun in the labs;
Installation of casework, fume hoods and countertops is complete on all
floors; Final mechanical, electrical and plumbing connections are in
progress on all floors.
January 2002Limestone steps are being installed at the west entrance; Ceiling grid is
being installed on the second floor; Casework installation is substantially
complete on the second and third floors;  Cleanroom walls and ceiling grid
installation is complete; Final connections for the lab services have begun
on the second floor.
December 2001Slate and copper roof is complete; Stucco work is compete at the portico;
Drywall installation is in progress (offices) on the second and third
floors; Painting is in progress on the second and third floors; Installation
of the casework and fume hoods has begun on the second floor.
November 2001Stucco work has started on the Portico; Slate and copper is
substantially complete on all elevations except the west elevation; Painting
is in progress on all floors (masonry walls);   Rough-in for the laboratory
services is in progress on the second and third floors;  Installation of the
first floor clean room is in progress.
October 2001Precast installation is complete on the west elevation; Window
installation is complete; Painting of the exterior windows is in progress;
Interior metal studs are complete and gypsum wall board is in progress on
the second floor;  Painting has begun on the second floor;  Start-up of two
of the AHU's has taken place.
September 2001Brick installation is complete on all elevations; Precast
installation is in progress on the west elevation; Hand carved limestone
capitals have been set in place; Slate and copper work continues on the
roof; Window installation is 85% complete; Interior metal stud walls are
complete on the second and third floors;  Mechanical and electrical rough-in
continues on all floors.
August 2001The copper and slate roof work has begun on the north and east
elevations.
July 2001Brickwork is complete on all elevations except the west elevation.
Interior block walls are complete on all floors.
June 2001Brickwork continues on the south and north elevations.  Interior
block walls are complete on the second and third floors and in progress on
the first floor.  Rough-in of the mechanical and electrical systems is in
progress on the second and third floors.
May 2001Interior block walls are going up on the second and third floors.
April 2001Exterior brickwork has begun on the roof parapet and chimneys.
Rough-in of the mechanical and electrical systems is in progress on the
second floor.
March 2001The roof is begun.
February 2001The front pillars are put in place!
January 2001Steel erection continues; floors begin to be placed.
 
December 2000It's beginning to look like a building now!
 
November 2000Structural steel begins.
 
October 2000Footings and foundations are completed.
 
September 2000Footings and foundation walls begin.
August 2000Structural fill replaces soils removed at the site.
 
July 2000Demolition begins.
 
June 2000Site preparation and set up on The Mall under way.
 
 |  |  |  
 |  |