If you experience difficulties viewing these clips, please download the most recent version of the Quicktime plug-in. See a complete time lapse to-date, or select by month below.


  • September 22, 2002
    P.S. Du Pont Hall dedication
  • May 2002
  • April 2002
  • March 2002
    Restoration of the Green landscaping and pavers in is progress; Ceramic tile installation is complete in the toilet rooms and accessories installation is in progress; Millwork installation has begun in the Dean's Suite and the Lobby.
  • February 2002
    Limestone steps and pavers are complete at the west entrance; Drywall installation is complete on all floors; Ceramic tile is being installed in the toilet rooms; Sheet vinyl installation has begun in the labs; Installation of casework, fume hoods and countertops is complete on all floors; Final mechanical, electrical and plumbing connections are in progress on all floors.
  • January 2002
    Limestone steps are being installed at the west entrance; Ceiling grid is being installed on the second floor; Casework installation is substantially complete on the second and third floors; Cleanroom walls and ceiling grid installation is complete; Final connections for the lab services have begun on the second floor.
  • December 2001
    Slate and copper roof is complete; Stucco work is compete at the portico; Drywall installation is in progress (offices) on the second and third floors; Painting is in progress on the second and third floors; Installation of the casework and fume hoods has begun on the second floor.
  • November 2001
    Stucco work has started on the Portico; Slate and copper is substantially complete on all elevations except the west elevation; Painting is in progress on all floors (masonry walls); Rough-in for the laboratory services is in progress on the second and third floors; Installation of the first floor clean room is in progress.
  • October 2001
    Precast installation is complete on the west elevation; Window installation is complete; Painting of the exterior windows is in progress; Interior metal studs are complete and gypsum wall board is in progress on the second floor; Painting has begun on the second floor; Start-up of two of the AHU's has taken place.
  • September 2001
    Brick installation is complete on all elevations; Precast installation is in progress on the west elevation; Hand carved limestone capitals have been set in place; Slate and copper work continues on the roof; Window installation is 85% complete; Interior metal stud walls are complete on the second and third floors; Mechanical and electrical rough-in continues on all floors.
  • August 2001
    The copper and slate roof work has begun on the north and east elevations.
  • July 2001
    Brickwork is complete on all elevations except the west elevation. Interior block walls are complete on all floors.
  • June 2001
    Brickwork continues on the south and north elevations. Interior block walls are complete on the second and third floors and in progress on the first floor. Rough-in of the mechanical and electrical systems is in progress on the second and third floors.
  • May 2001
    Interior block walls are going up on the second and third floors.
  • April 2001
    Exterior brickwork has begun on the roof parapet and chimneys. Rough-in of the mechanical and electrical systems is in progress on the second floor.
  • March 2001
    The roof is begun.
  • February 2001
    The front pillars are put in place!
  • January 2001
    Steel erection continues; floors begin to be placed.
  • December 2000
    It's beginning to look like a building now!
  • November 2000
    Structural steel begins.
  • October 2000
    Footings and foundations are completed.
  • September 2000
    Footings and foundation walls begin.
  • August 2000
    Structural fill replaces soils removed at the site.
  • July 2000
    Demolition begins.
  • June 2000
    Site preparation and set up on The Mall under way.