| GRANTS DATA MIGRATION PLAN: Last updated: 3-30-04 | ||||||||||||
| Data Conv. Datasets | Priority | Format-Source | Who preparing | Preparation Status & Steps | Date Due | Actual Given | Who Converting | Date Due | Actual Completed | Conver. Status | Notes | |
| Keywords | L | Excel | Depts/ Chris | ü | Ready | Jay/John | DONE | |||||
| Professional Data | H | Excel | HR/Depts/Chris | Round 1 Data Load: In Progress | ||||||||
| Status: 3-31 John has partially run in data- | ||||||||||||
| ü | Provide Round 1 Data Set | 26-Mar | ||||||||||
| Run App Engine with Round 1 Data | 29-Mar | John/Lyn | 5-Apr | some clean up required; John and Chris working on this; should be finished by 4/1/04 to be ready for a final load by 5-Apr. | ||||||||
| Validate Round 1 Data Run | 5-Apr | Chris & Susan/Anna | 6-Apr | |||||||||
| Round 2 Data Load: | 5-Apr | |||||||||||
| Status: | ||||||||||||
| Provide Round 2 Data Set | 5-Apr | Chris | ||||||||||
| Run App Engine with Round 2 Data | 10-Apr | John/Lyn | ||||||||||
| Validate Round 2 Data Run | 15-Apr | Chris & Susan/Anna | ||||||||||
| Round 3 Data Load: | ||||||||||||
| Status: | ||||||||||||
| Provide Round 3 Data Set | 25-Apr | |||||||||||
| Run App Engine with Round 3 Data | 28-Apr | John/Lyn | ||||||||||
| Validate Round 3 Data Run | 1-May | Chris & ? | ||||||||||
| HR IT load Prior Work Experience, Memberships, Certifications | ||||||||||||
| Status: | ||||||||||||
| Provide Data Set | 15-Apr | WE is round 1, Memberships is Round 2, Certifications is round 3--total data set provided by 15-April, but per the dates above, each will be provided sequentially. | ||||||||||
| Run SQR? with Data | John/Mary | 26-Apr | ||||||||||
| Validate Data Run | Chris & Anna | 30-Apr | ||||||||||
| Integration Broker | ||||||||||||
| Status: (3-30) Discovered issue with the PERS_DATA_EFFDT table (mismatch of data elements) between HR and FIN. John is researching. | John Adcock working toward a resolution. | |||||||||||
| Billing History | H | Billing Team | Met to plan. | ????? | Jim & Rick | ????? | ||||||
| HR Dept. Locatns. | H | Gerri and Process Subteam | In process - 75% complete (3-30), FIDEV | 15-Apr | none | |||||||
| Move to FITST | ||||||||||||
| Move to FIPRD | ||||||||||||
| Sponsors | H | Excel | Data Migra. Team | Status - (4-2) Gerri is waiting (asked Rick) for the correct format- she doesn't know what that is. (4-1) The files were received on 4/1 but would not load successfully because cust_id.txt was not in the correct format. (3-18)Test Sponsors loaded. Identified problem with Vendor SetID. John corrected program. Second test data to be given to John on 3/31. | 37 loaded 3-18-04 505 Sponsors identified, gathering addresses- have 120. | |||||||
| Initial Test Load: FIDEV | ||||||||||||
| Status: 3-31 Gerri will get 2nd data set to John | ||||||||||||
| ü | Provide Test Sponsor Data Set | 18-Mar | 37 records | |||||||||
| ü | Run SQR with Test Data | John | 18-Mar | |||||||||
| ü | Validate Test Sponsor Data Run | |||||||||||
| ü | Provide Second Test Sponsor Data Set | 31-Mar | 1-Apr | 518 Sponsor Records | ||||||||
| Run SQR with Second Test Data | John | 31-Mar | ||||||||||
| Validate Second Test Sponsor Data Run | 1-Apr | |||||||||||
| Full Test Load: FITST? | Depends on avail. of FITST- must have SP1 and ALL Fix packs 1 & 2 loaded. | |||||||||||
| Status: | ||||||||||||
| Provide Final Test Sponsor Data Set | 7-Jun | 500+ records | ||||||||||
| Run SQR with Final Test Data | John | 7-Jun | ||||||||||
| Validate Final Test Sponsor Data Run | 10-Jun | |||||||||||
| Reload all Data on FIPRD: ??????? | Depends on avail. of FITST- must have SP1 and ALL Fix packs 1 & 2 loaded. | |||||||||||
| Status: | ||||||||||||
| Provide Final Sponsor Data Set | 23-Jun | |||||||||||
| Run SQR with Final Sponsor Data | John | 23-Jun | ||||||||||
| Validate Final Sponsor Data Load | 24-Jun | |||||||||||
| Proposals (SQR) | H | Semi-colon Delimited | Data Migra. Team | Initial Test Load: on FIDEV | ||||||||
| Status(3-30) - Test Proposal loaded. Identified problem with leading zeros and Department Contact. John will revise the program and load second proposal. | ||||||||||||
| ü | Provide Test Award Data Set | 24-Mar | ||||||||||
| ü | Run SQR with Test Data | John | 25-Mar | |||||||||
| ü | Validate Test Award Data Run | 29-Mar | ||||||||||
| Provide Second Test Award Data Set | 31-Mar | |||||||||||
| Run SQR with Second Test Data | John | 31-Mar | ||||||||||
| Validate Second Test Award Data Run | 31-Mar | |||||||||||
| ü | Provide Test Award Budget Data Set | 31-Mar | 1-Apr | |||||||||
| Run SQR with Test Budget Data | John | 1-Apr | ||||||||||
| Validate Test Award Budget Data Run | 2-Apr | |||||||||||
| Full Test Load: on FIDEV??? | ||||||||||||
| Status: (4-1) Jay provided a preliminary extract- Gerri needs to discuss further with Jay on Monday., not usable at this point. | ||||||||||||
| ü | IT provide Legacy extract Award data | Jay | 1-Apr | |||||||||
| Tic and Tye Data Stream to Legacy | 14-Apr | |||||||||||
| Provide Full Award (Proposal) Data | 15-Apr | |||||||||||
| Run SQR with Award (Proposal) Data | John | 16-Apr | ||||||||||
| Validate Award (Proposal) Data | 7-May | |||||||||||
| IT provide Legacy extract Award Budget data | Jay | 7-May | ||||||||||
| Tic and Tye Data Stream to Legacy & PS | 19-May | |||||||||||
| Provide Full Award Budget(Proposal) Data | 20-May | |||||||||||
| Run SQR with Awd. Budget Prop. Data | John | 21-May | ||||||||||
| Validate Award Budget Proposal Data | 7-Jun | |||||||||||
| Reload Award Data on FITST | Depends on avail. of FITST- must have SP1 and ALL Fix packs loaded. | |||||||||||
| Status: | ||||||||||||
| Provide Full Award & Budget(Proposal) Data | 9-Jun | |||||||||||
| Run SQR with Awd. & Budget Prop. Data | John | 9-Jun | ||||||||||
| Validate Award Proposal Data | 14-Jun | |||||||||||
| Load Proposal Data on FITST | ||||||||||||
| Status: | ||||||||||||
| Provide Proposal and Budget Data | 15-Jun | |||||||||||
| Run SQR with Prop. Data | John | 15-Jun | ||||||||||
| Validate Proposal Data | 21-Jun | |||||||||||
| Final load of all Data on FIPRD | Depends on avail. of FIPRD- must have SP1 and ALL Fix packs loaded. | |||||||||||
| Status: | ||||||||||||
| Provide Award and Budget Data | 22-Jun | |||||||||||
| Run SQR with Award and Budget Data | John | 22-Jun | ||||||||||
| Validate Award and Budget Data | 23-Jun | |||||||||||
| In Grants P.S.- Create Awards | 24-Jun | |||||||||||
| Run SQL select to update Project Data | John | 28-Jun | ||||||||||
| Run SQl select to update Contracts Data | John | 28-Jun | ||||||||||
| Provide Proposal and Budget Data | 28-Jun | |||||||||||
| Run SQR with Prop. Data | John | 28-Jun | ||||||||||
| Validate Proposal Data | 29-Jun | |||||||||||
| Provide Ag 30's Data | 29-Jun | |||||||||||
| Run SQR with AG 30's Data | John | 29-Jun | ||||||||||
| Validate AG 30's Data | 30-Jun | |||||||||||
| Cang_Budg records (Ledger Budg)to Ledger_Proj | H | Status: 3-31- Tamara will discuss with John | ||||||||||
| Move budget records from 1 table to another | June | John | ||||||||||
| Tic and Tye 2 tables | ||||||||||||
| Change Balance Load SQR to go to Ledger_proj | John | |||||||||||
| Ledger Transactions to Proj_Resource | H | Status: | ||||||||||
| Run Delivered Process to move Ledger Trans. To Proj_Resource | June | John | ||||||||||
| Tic and Tye Proj_Resource to Ledger | ||||||||||||
| Update to Project Tables | H | Data Migr. Team | Status: | |||||||||
| Rules Identified by Tamara, Rachel and Vanessa | 8-Apr | Vaness on Sick Leave | ||||||||||
| Test Update Tables by SQl select statements | John | 30-Jun | ||||||||||
| Update to Contract Tables | H | Data Migr. Team | Status: | |||||||||
| Rules Identified by Tamara, Rachel and Vanessa | 8-Apr | Vaness on Sick Leave | ||||||||||
| Test Update Tables by SQl select statements | John | 30-Jun | ||||||||||
| DA- AG 30s | M | Julie | Status: 3-31 Julie will create new conversion spreadsheet, ulie needs to talk with Tamara | |||||||||
| IT provide Legacy extract data | 7-May | Jay | ||||||||||
| Julie provide data | Jay | |||||||||||
| IT populate PS | Tim | |||||||||||